To deliver a waste water pumping station via our Modular Assembly Framework (MAF), that provides offsite built solutions for a pumping station to serve a Cala Homes East development with 64 households.

Scope
The project scope was to design, procure, manufacture, install and commission a Scottish Water standard product.
Delivering a wastewater pumping station that would not only meet the requirements prior to Scottish Water’s adoption process but provide the client with a first class service.

Our Service and Delivery
We were able to provide a unique “one-stop” service from design to telemetry commissioning of the wastewater pumping station within an 11 month period, which was only achievable through our collaborative partnership with Scottish Water and framework suppliers.

  • Client: Cala Homes
  • Services: Modular Assembly Framework
  • Sector: Development Market

“By utilising the standard product, Scottish Water knows what we are getting. The approval process becomes much more simplified, reducing typical timescales from 6-12months to 2-3weeks. The standard product is what we want, with certainty that the product is always to the same standard and specification.”
- Project Manager, Cala Homes