Project Scope:
_Overall project value £2.8M
_The main drivers for this project were to manage cryptosporidium and overall water quality.
_Upgrade washwater recovery system
_Upgrade disinfection control with new hypochlorite dosing and controls
|
Services Provided:
_Project Management of all MEICA content
_Procurement of all MEICA equipment including MCC, Pumps, PLC
_Interface PLC design, build, install and commission
_Mechanical and Electrical installation and commissioning
_Operative training
_Telemetry software, installation and commissioning
_Optional process commissioning
|